An Offshore Field Engineer experienced in Offshore Subsea Structure Installation, Subsea Cable Lay Vessel Mobilization, Methods, Construction Support & ROV Inspection in the Oil & Gas EPCI industry in Qatar.
Graduated from the University of Strathclyde, UK with a Master's degree in Marine Engineering, specializing in hull condition assessment using artificial intelligence.
Name
Ram Prasad Ramakrishnan
Position
Offshore Field Engineer
Experience
4+ Years
Availability
Full-time / Rotation
McDermott International
Qatar
Managed offshore vessel mobilization and installation operations for the NFXP campaign, ensuring procedural compliance and seamless execution across stakeholders.
893 structures including Steel Bridges, Steel Sleepers, ZRB Sleepers, Concrete Sleepers & Mattresses using DP vessel
269KMs of Subsea Cable transpooled onto Cable Lay DP Vessel mobilized from China to Qatar
6 x Temporary looping platforms installed on Jacket platforms SIMPOS with Drill rigs
Fabricated DIY reflectors using SOLAS approved reflective tapes for DP reference compliance
Inspection of thickness deterioration on pre-installed MEG risers on Jacket Platforms
SAAR Global Services L.L.C
Qatar
Conducted vessel, cargo, and container surveys, while managing port operations to support safe and timely loading and discharge.
University of Strathclyde
Glasgow, United Kingdom • 2017 – 2018
MODULES: Advanced Marine Engineering, System Availability and Maintenance, Maritime Safety and Risk, Marine Environment Protection
DISSERTATION: Hull Condition Assessment using Artificial Intelligence
Sri Ramakrishna Engineering College
Anna University, India • 2013 – 2017
MODULES: Dynamics, Materials, Structural Mechanics, Thermodynamics, Fluid Mechanics
DISSERTATION: Air Assisted Windshield Wiper System in Automobiles

Riser Inspection on Pre-Installed Jackets using ROV's to ascertain thickness deterioration due to water ingress

Loadout & Installation of 626 Subsea structures including steel bridges, sleepers, and concrete mattresses

Installation of 267 Subsea structures and 6x Temporary Looping Platforms on jackets SIMOPS with Drill rigs

Installation of Stern chute, Roller tables & Tugger winches. Mobilized Platform Support Vessel with heave compensated gangway